Hwy 417 Ramp Closures

Carling Westbound Off-Ramp Closure – The Carling Westbound off-ramp is closed for a period of 4 weeks. 

Maitland Eastbound On and Off-Ramps – The Maitland Avenue Eastbound on and off-ramps will be closed for a period of 2 weeks. This is currently scheduled for May 16*, 2019.

Highway 417 Full Closure – Highway 417 will be fully closed for a period of 17 hours currently scheduled on the weekend of August 10*, 2019. This is required to facilitate the rehabilitation of the Merivale Road structure. Highway 417 traffic will use the approved City detour during this event.

Carling Eastbound On-Ramp Closure – The Carling Eastbound on-ramp will be closed for a period of 7 weeks to accommodate the widening of Highway 417 and the rehabilitation of the Merivale Road structure. This is currently scheduled for August 15*, 2019.

Please note that the dates marked with an asterix (*) are still tentative and could change, depending on construction progress. Follow Riley Brockington and the Carlington Community Association on twitter at @RiverWardRiley and @CarlingtonCA for updates on closures dates as the information is finalized and closures are approaching.